CHURCH BUILDING PROGRESS
(LATEST UPDATE
AT BOTTOM)
Construction Photos -- Click Here
- >
| Caney Baptist Church Building Project | ||||
| Project Time Performance Tracking | ||||
| Project Assignment | Project Type | Estimated Start | Estimated Finish | Finish Date |
| Phase I - Preparation | ||||
| Jerry Moore / Kevin / Randy | License/Permit Approvals | 15-Dec-2007 | 15-Jan-2008 | 15-May-2008 |
| Burnis Jacobs / Kenneth | Footer & Block | 10-Mar-2008 | 21-Mar-2008 | 24-Mar-2008 |
| Tim Watts | Plumbing Rough-In | 1-Apr-2008 | 15-Apr-2008 | 30-Apr-2008 |
| Brock Slone | Electric Rough-In | 1-Apr-2008 | 15-Apr-2008 | 30-Apr-2008 |
| Jerry Moore / Haskel | Lay Drainage Pipes | 1-Apr-2008 | 15-Apr-2008 | 30-Apr-2008 |
| Mary Lois Jacobs | Spray for Bugs | 1-Apr-2008 | 5-Apr-2008 | 30-Apr-2008 |
| Jerry Moore | Order Concrete/Equipment | 10-Apr-2008 | 12-Apr-2008 | 30-Apr-2008 |
| Sean | Pour Slab | 15-Apr-2008 | 30-Apr-2008 | 30-Apr-2008 |
| Phase II - Selection | ||||
| Committee / Church Vote | Choose Roofing, Siding, Stone | 1-Dec-2007 | 31-Dec-2007 | 3-Feb-2008 |
| Committee | Choose Windows, Doors, Lights | 1-Jan-2008 | 31-Jan-2008 | 2-May-2008 |
| Committee | Choose Pews vs. Chairs | 1-Feb-2008 | 28-Feb-2008 | 2-May-2008 |
| Committee | Choose Appliances/Fixtures | 1-Mar-2008 | 31-Mar-2008 | 30-Apr-2008 |
| Committee / Church Vote | Choose Carpet vs. Wood Floors | 1-Apr-2008 | 30-Apr-2008 | 30-Apr-2008 |
| Jerry Moore / Dave | Order All Construction Materials | 1-Jan-2008 | 1-Jun-2008 | 25-May-2008 |
| Phase III - Construction | ||||
| Jerry Moore / Burnis | Materials Delivered to Site | 15-May-2008 | 25-May-2008 | 25-May-2008 |
| Jerry Moore | Rent Crane, Scaffolding, etc. | 15-May-2008 | 31-May-2008 | 25-May-2008 |
| Carpenters for Christ | Under-Roof Construction | 2-Jun-2008 | 13-Jun-2008 | 12-June-2008 |
| Bold Mission Builders | Exterior/Interior Construction | 16-Jun-2008 | 27-Jun-2008 | 27-Jun-2008 |
| First Baptist Church of Jacksonville | Interior Construction | 5-Jul-2008 | 11-Jul-2008 | 11-Jul-2008 |
| Clearview Baptist Church | Interior Construction | 7-Jul-2008 | 11-Jul-2008 | 11-Jul-2008 |
| Marion County Baptist Assoc. | Interior Construction | 13-Jul-2008 | 19-Jul-2008 | 19-Jul-2008 |
| Melrose Baptist Church | Interior Construction | 19-Jul-2008 | 25-Jul-2008 | 25-Jul-2008 |
| Phase IV - Finishing | ||||
| Members / Volunteer Groups | Painting, Trim, Flooring, etc. | 1-Jul-2008 | 31-Dec-2008 | 3/7/2009 |
| Committee | Furnishings | 1-Jul-2008 | 31-Dec-2008 | 3/7/2009 |
PROGRESS UPDATE AS OF JUNE 30, 2008
January
* Exterior Siding/Roofing/Stone
was chosen:
Gray Scheme as voted upon.
* Steeple and Baptistry
were ordered: 25-ft. Steeple with Cross - Bone color
selected for baptistry.
February
* Permit
for the Footers and Slab was received from the state!
* Gravel was spread on the parsonage
drive and the drive to the building site.
* Plumbing
Plan was completed.
March
*
Windows were donated by an organization in Winchester, Kentucky,
saving us $6,000 or more.
* Footers
and foundation blocks were completed.
April
*
In-slab electric and plumbing was done in
April.
* Port-a-potties
were ordered and delivered to site in April.
* Slab was poured in
April by Shon of Carpenters for Christ,
saving us several thousand dollars.
May
* Preliminary
landscaping
was done to put dirt around the foundation and Gravel
was placed on the ground to help with mud and loose soil.
* Building Package arrived on
May 30th. Crane, fork-lift and scissor-lift
were ordered.
* Steeple and Baptistry
were delivered to building site by Carpenters for Christ
volunteers, Bill and Joan, saving us $1,000 or more in
delivery charges.
June
* Carpenters for Christ group of
100+ professionals began arriving on June 1st.
Between June 3rd and June 12th, they put the building under roof, installed windows, doors,
baptistry, and set the steeple.
* Bold Mission Builders Group 1 arrived
on June 15th and Group 2
arrived on June 22nd. Between the two groups,
the exterior siding and
roofing were finished, much of the electric was roughed-in, insulation was
installed on most outer walls and sanctuary walls, and sheetrock was put up in
the Sunday school wing and the pastor's study.
* Plumbing was roughed in and
passed inspection.
* HVAC duct work and units were
installed.
July
* Electric will be completed; insulation and sheetrock
will be installed; drywall finishing will begin; light fixtures, interior doors,
and flooring will be installed as workers are available.
* Volunteer Groups scheduled to come this summer:
June
1 - 14 Carpenters for Christ
(Alabama)
Group of 100 men will put Church under roof
June 6 - 14
Victor Baptist Church
(South Carolina)
Will host Vacation Bible School for us
and help where needed.
June 15 - 27
Bold Mission
Builders (Georgia)
of the Stone Mountain Baptist Association
is sending approximately 85 men the first week
and
20 the second week.
July
5 - 11 First
Baptist Church of Jacksonville (Alabama)
Group of 25 will help with interior work.
July
7 - 11 Clearview
Baptist Church (South Carolina)
Group of 30 will help with interior work.
July 13 - 19 Marion
County Baptist Association (Alabama)
Group of 80 - 30 to 35 men will
work at church site while young people will
be hosting activities for local youth.
July 19 - 25 Melrose
Baptist Church (Virginia)
group of 25 coming to do finish work. A block party
will be held for young people.
October,
November, December Various Small Groups
(South Carolina)
Hang Sheetrock, Finish Sheetrock, Paint.
* Continue to pray that the right groups will come at the right times!
Building Committee Members:
Jerry Moore, Project Manager
Burnis Jacobs, Assistant Manager
Margo Sparkman, Treasurer
Mary Lois Jacobs, Reporter
Donna Dudte, Prayer Warrior
Shelia Jacobs, Secretary
Ann Moore, Food-Hospitality Coordinator
Tim Watts, Plumbing Advisor
Kenneth Sparkman, Electrical Advisor
SUB-COMMITTEES:
FOOD/HOSPITALITY COMMITTEE
Kitchen Duty (Serving/Cleanup)
Dessert Preparation and/or Delivery
Food Donations Solicitation/Monitoring
Click
Here for a List of Special Items Needed for Groups
Housing for Groups and/or Representatives
EXTERIOR
Siding/Brick/Stone
Windows
Entrance Doors
Steeple
Signage
Landscaping
INTERIOR DESIGN
Color Scheme
Stable Furnishing
Doors
Lighting
Painting
Hardware/Trim/Accents
Carpeting/Tile
INTERIOR FURNISHING
Pulpit
Pews
Tables
Chairs
Offices
Classrooms
Restrooms
KITCHEN/RECEPTION HALL
Dining Hall Arrangement
Appliances
Cabinets
Window Treatments
Decor
SOUND & VIDEO
Music System
Microphone/Speaker System
Video System
Recording System